Capital Projects
Start Date: August 2022
Estimated Completion Date: October 2022
The Bob McMeekin Park Upgrade Project is will restore the damage done to the park during the flood and provide;
- an outdoor amphitheatre
- 2 tiered amphitheatre seating
- a larger toboggan hill
- expanded parking
- a new firepit
- landscaping
- and will be home to the new Town of Hay River Welcome Sign
Start Date: July 2022
Estimated Completion Date: October 2022
Rowes Construction will be managing this project which will put in a new water line and replace the pavement and sidewalks. Rowes can be reached at:
Angus Pardy (709-884-7368), Site Superintendent
Watch for future updates on the Town of Hay River Facebook Page.
Step 1: Fusion and Drilling
Step 2: Building services, hydrants, and valve installation
Phase 1 Work Zone: Approx. 50 meters in length
Phase 2 Work Zone: Approx. 45 meters in length
Phase 3 Work Zone: Approx. 45 meters in length
Phase 4 Work Zone: Approx. 10 meters in length
Phase 5 Work Zone: Approx. 40 meters in length
Phase 6 Work Zone: Approx. 10 meters in length
Phase 7 Work Zone: Approx. 15 meters in length.
If you have any questions or would like further clarification, please contact:
Angus Pardy (709-884-7368), Site Superintendent
If you require further assistance, please call public works at 867-875-7030
Start Date: July 2022
Projected Completion Date: October 2022
Watch for future updates on the Town of Hay River Facebook Page.
Rowes Construction are managing this 2 year project. They can be reached at:
Ron Brady, Site Superintendent: 709-743-3111
Year 1 of the project will be to replace the underground services and Year 2 will see the road paved.
Rowes will be installing a new water line and upgrading the storm system. The road will be paved in 2023.
YEAR 1
Phase 1 Work Zone: Approx. 185 meters in length and 3 weeks to complete
Phase 1 will be the drilling and installation of the water line at the South end of Industrial Drive, as well as the installation of service connections, valves, fire hydrants, and tie-ins. The Southbound traffic lane will be closed for the duration of this phase but access to parking lots will remain accessible.
Phase 2 Work Zone: Approx. 200 meters in length and 3 weeks to complete
Phase 2 will include the installation of the storm sewer at the North end of Industrial Drive. As it is being trenched, it will require full road closure during the day. We will ensure access to parking lots will remain open for the businesses in this work area.
Phase 3 Work Zone: Approx. 215 meters in length and 1 week to complete
Phase 3 consists of the culvert installation. A total of 4 culverts needs to be installed. The installation of these does not require very deep trenching so traffic disruption will be kept to a minimum. Access to driveways will need to be disrupted during the installation of culverts but should only be 1 day or less for each culvert.
YEAR 2 – 2023
If you have any questions or would like further clarification, please contact:
Ron Brady, Site Superintendent: 709-743-3111
If you require further assistance, please call public works at 867-875-7030
Start Date: August 2020
Estimated Completion Date: August 2022
The new sanitary lift station is nearing completion and will be put in service shortly.
Start Date: March 2022
Estimated Completion Date: October 2022
A Public Hearing was held on March 17, 2021 with Council to rezone the land that would be developed into the Fraser Place Subdivision.
A copy of the Public Presentation is available here.
This project is being managed by Blackstone Homes at:
Mike Unger 780 285 9081
Phase 1 of the project started in March 2022 with site clearing and installation of utilities. Lot sales will commence once Phase 1 is complete and the updated flood mapping is received. Phase 2 will be the installation of sidewalk, gutters and paving.
Start Date: August 2022
Estimated Completion Date: October 2022
The Golf Course Road will be improved for condition and better drainage.